Hi,
I was trying to schedule a report this morning (not built by me, but by another company) that would send/generate the report to our business team on a weekly basis (instead of daily) and was surprised to see that you could not do this from the Reporting Services Web Console. I.e., something akin to "=Today -7" or "Last week" or anything...
There are a number of solutions around building custom tables and data-driven features into your own reports - which I have done - but how does one handle the scenario when the rdl files are not their own?
If I modify these custom reports by another organization, I am effectively nullifying my warranty for their work and will not be able to get support should there be a problem with the report?
Has anyone else hit this issue? Is the onus on the company to build this flexibility into all of their reports?
Thanks - Greg